Hyderabad: Land acquisition process for Northern section of Regional Ring Road (Triple R) The latest controversy has started. Officials are preparing to distribute compensation on the basis of government-assessment rates, yet the final amount is not being agreed.
However, Farmers are rejecting compensationClaiming that it is less than half the market price. Officers now plan Deposit money in court And move together Forced acquisitionA step that can cause a big disturbance Lagadpalli case,
Land acquisition scope and compensation estimate
The northern section of the Triple R Project extends 162 kmNeed to acquire 1,950 hectares Role. Total estimated compensation Nearby for landlords and affected parties ₹ 5,100 CroreTo be shared by Central and state governmentsIn this, state government ₹ 2,550 crore is responsible.
The current state budget is kept in ₹ 1,250 Crore For the acquisition, and according to the officials, 85% of land acquisition is allegedly completedThe awards have been passed, and NHAI is preparing to deposit compensation directly in farmers' accounts,
Follow for more information: munsifdally.com
Farmers strongly opposed insufficient compensation
Farmers argue that Offered ₹ 6 lakh per acre Is quite low Market Price ₹ 40- ₹ 50 Lakh AcreEven with an amendment, the highest proposed rate from the government is only ₹ 12-15 lakh per acre. In response, the government plans Start arbitration through district collectors To assure compensation.
Farmers are refusing to participate with their land until they are paid Current market ratesCriticize Ignore the proper consultation And proceed unilaterally with prize announcements.
ALSO READ: Thieves stole gold and cash from couple to Hyderabad in train
Legal resistance and forcible land acquisition threat
Farmers continued to reject the proposed compensation, NHAI is preparing to deposit money in court And move together Legal land acquisition and ownership transfer (mutation),
Farmers have vowed not to surrender their land Appropriate compensation Has been given Some have already contacted the courts, Order to stay safeThis issue is more complex than previous promises Ranga Reddy and Yadadari districts Remember that R&B Minister Komatidid Venkat Reddy He was assured that the RRR route would not affect their land.
Project delay due to legal and environmental obstacles
However tender Triple R Northern Section Construction She is swimming, they remain uncontrolled due to this Pending legal dispute and environmental withdrawal issuesOfficials have now confirmed Approval has been obtainedAnd they hope that soon legal challenges will be resolved.
Should the farmers remain in their denial, the government's plan Submit compensation in court And continue with the acquisition, potentially ignite further resistance.